§6.504 Consultation during the facilities planning process.
(a) General. Consistent with 40 CFR 1501.2 and 35.2030(c), the responsible official shall initiate the environmental review process early to identify environmental effects, avoid delays, and resolve conflicts. The environmental review process should be integrated throughout the facilities planning process. Two processes for consultation are described in this section to meet this objective. The first addresses projects awarded Step 1 grant assistance on or before December 29, 1981. The second applies to projects not receiving grant assistance for facilities planning on or before December 29, 1981 and, therefore, subject to the regulations implementing the Municipal Wastewater Treatment Construction Grant Amendments of 1981 (40 CFR part 35, subpart I).
(b) Projects receiving Step 1 grant assistance on or before December 29, 1981. (1) During facilities planning, the grantee shall evaluate project alternatives and the existence of environmentally important resource areas including those identified in §6.108 and §6.509 of this subpart, and potential for open space and recreation opportunities in the facilities planning area. This evaluation is intended to be brief and concise and should draw on existing information from EPA, State agencies, regional planning agencies, areawide water quality management agencies, and the Step 1 grantee. The Step 1 grantee should submit this information to EPA or a delegated State at the earliest possible time during facilities planning to allow EPA to determine if the action is eligible for a categorical exclusion. The evaluation and any additional analysis deemed necessary by the responsible official may be used by EPA to determine whether the action is eligible for a categorical exclusion from the substantive environmental review requirements of this part. If a categorical exclusion is granted, the grantee will not be required to prepare a formal EID nor will the responsible official be required to prepare an environmental assessment under NEPA. If an action is not granted a categorical exclusion, this evaluation may be used to determine the scope of the EID required of the grantee. This information can also be used to make an early determination of the need for partitioning the environmental review or for an EIS. Whenever possible, the Step 1 grantee should discuss this initial evaluation with both the delegated State and EPA.
(2) A review of environmental information developed by the grantee should be conducted by the responsible official whenever meetings are held to assess the progress of facilities plan development. These meetings should be held after completion of the majority of the EID document and before a preferred alternative is selected. Since any required EIS must be completed before the approval of a facilities plan, a decision whether to prepare an EIS is encouraged early during the facilities planning process. These meetings may assist in this early determination. EPA should inform interested parties of the following:
(i) The preliminary nature of the Agency's position on preparing an EIS;
(ii) The relationship between the facilities planning and environmental review processes;
(iii) The desirability of public input; and
(iv) A contact person for further information.
(c) Projects not receiving grant assistance for Step 1 facilities planning on or before December 29, 1981. Potential Step 3 or Step 2+3 grant applicants should, in accordance with §35.2030(c), consult with EPA and the State early in the facilities planning process to determine the appropriateness of a categorical exclusion, the scope of an EID, or the appropriateness of the early preparation of an environmental assessment or an EIS. The consultation would be most useful during the evaluation of project alternatives prior to the selection of a preferred alternative to assist in resolving any identified environmental problems.