| Home | 29 CFR | 40 CFR | 49 CFR | Federal Register | MSDS Search | Purchase CFR e-Books |
1.0 Model Facility-Specific Response Plan
1.1 Emergency Response Action Plan
1.2 Facility Information
1.3 Emergency Response Information
1.3.1 Notification
1.3.2 Response
Equipment
List
1.3.3 Response
Equipment
Testing/Deployment
1.3.4 Personnel
1.3.5 Evacuation
Plans
1.3.6 Qualified
Individual's Duties
1.4 Hazard Evaluation
1.4.1 Hazard
Identification
1.4.2 Vulnerability
Analysis
1.4.3 Analysis
of the Potential for an Oil
Spill
1.4.4 Facility
Reportable Oil Spill History
1.5 Discharge Scenarios
1.5.1 Small and
Medium
Discharges
1.5.2 Worst
Case Discharge
1.6 Discharge Detection Systems
1.6.1 Discharge
Detection By
Personnel
1.6.2 Automated
Discharge Detection
1.7 Plan Implementation
1.7.1 Response
Resources for Small, Medium, and Worst Case
Spills
1.7.2 Disposal
Plans
1.7.3 Containment
and Drainage Planning
1.8 Self-Inspection, Drills/Exercises, and
Response Training
1.8.1 Facility
Self-Inspection
1.8.1.1 Tank
Inspection
1.8.1.2 Response
Equipment
Inspection
1.8.1.3 Secondary
Containment
Inspection
1.8.2 Facility
Drills/Exercises
1.8.2.1 Qualified
Individual Notification Drill
Logs
1.8.2.2 Spill
Management Team Tabletop Exercise
Logs
1.8.3 Response
Training
1.8.3.1 Personnel
Response Training
Logs
1.8.3.2 Discharge
Prevention Meeting Logs
1.9 Diagrams
1.10 Security
2.0 Response Plan Cover Sheet
3.0 Acronyms
4.0 References
(A) Owners or operators of facilities regulated under this part which pose a threat of substantial harm to the environment by discharging oil into or on navigable waters or adjoining shorelines are required to prepare and submit facility-specific response plans to EPA in accordance with the provisions in this appendix. This appendix further describes the required elements in §112.20(h).
(B) Response plans must be sent to the appropriate EPA Regional office. Figure F-1 of this Appendix lists each EPA Regional office and the address where owners or operators must submit their response plans. Those facilities deemed by the Regional Administrator (RA) to pose a threat of significant and substantial harm to the environment will have their plans reviewed and approved by EPA. In certain cases, information required in the model response plan is similar to information currently maintained in the facility's Spill Prevention, Control, and Countermeasures (SPCC) Plan as required by 40 CFR 112.3. In these cases, owners or operators may reproduce the information and include a photocopy in the response plan.
(C) A complex may develop a single response plan with a set of core elements
for all regulating agencies and separate sections for the
non-transportation-related and transportation-related components, as described
in §112.20(h). Owners or operators of large facilities that handle, store, or
transport oil at more than one geographically distinct location (e.g., oil
storage areas at opposite ends of a single, continuous parcel of property)
shall, as appropriate, develop separate sections of the response plan for each
storage area.
Several sections of the response plan shall be co-located for easy access by
response personnel during an actual emergency or oil discharge. This collection
of sections shall be called the Emergency Response Action Plan. The Agency
intends that the Action Plan contain only as much information as is necessary to
combat the discharge and be arranged so response actions are not delayed. The
Action Plan may be arranged in a number of ways. For example, the sections of
the Emergency Response Action Plan may be photocopies or condensed versions of
the forms included in the associated sections of the response plan. Each
Emergency Response Action Plan section may be tabbed for quick reference. The
Action Plan shall be maintained in the front of the same binder that contains
the complete response plan or it shall be contained in a separate binder. In the
latter case, both binders shall be kept together so that the entire plan can be
accessed by the qualified individual and appropriate spill response personnel.
The Emergency Response Action Plan shall be made up of the following sections:
1. Qualified Individual Information (Section 1.2) partial
2. Emergency Notification Phone List (Section 1.3.1) partial
3. Spill Response Notification Form (Section 1.3.1) partial
4. Response Equipment List and Location (Section 1.3.2) complete
5. Response Equipment Testing and Deployment (Section 1.3.3) complete
6. Facility Response Team (Section 1.3.4) partial
7. Evacuation Plan (Section 1.3.5) condensed
8. Immediate Actions (Section 1.7.1) complete
9. Facility Diagram (Section 1.9) complete
The facility information form is designed to provide an overview of the site
and a description of past activities at the facility. Much of the information
required by this section may be obtained from the facility's existing SPCC Plan.
1.2.1 Facility name and location:
Enter facility name and street address. Enter the address of corporate
headquarters only if corporate headquarters are physically located at the
facility. Include city, county, state, zip code, and phone number.
1.2.2 Latitude and Longitude: Enter
the latitude and longitude of the facility. Include degrees, minutes, and
seconds of the main entrance of the facility.
1.2.3 Wellhead Protection Area:
Indicate if the facility is located in or drains into a wellhead protection area
as defined by the Safe Drinking Water Act of 1986 (SDWA). 1
1A wellhead protection area is defined as the surface and
subsurface area surrounding a water well or wellfield, supplying a public water
system, through which contaminants are reasonably likely to move toward and
reach such water well or wellfield. For further information regarding State and
territory protection programs, facility owners or operators may contact the SDWA
Hotline at 1-800-426-4791. 1.2.4 Owner/operator: Write the
name of the company or person operating the facility and the name of the person
or company that owns the facility, if the two are different. List the address of
the owner, if the two are different.
1.2.5 Qualified Individual: Write
the name of the qualified individual for the entire facility. If more than one
person is listed, each individual indicated in this section shall have full
authority to implement the facility response plan. For each individual, list:
name, position, home and work addresses (street addresses, not P.O. boxes),
emergency phone number, and specific response training experience.
1.2.6 Date of Oil Storage Start-up:
Enter the year which the present facility first started storing oil.
1.2.7 Current Operation: Briefly
describe the facility's operations and include the North American Industrial
Classification System (NAICS) code.
1.2.8 Dates and Type of Substantial
Expansion: Include information on expansions that have occurred at the
facility. Examples of such expansions include, but are not limited to:
Throughput expansion, addition of a product line, change of a product line, and
installation of additional oil storage capacity. The data provided shall include
all facility historical information and detail the expansion of the facility. An
example of substantial expansion is any material alteration of the facility
which causes the owner or operator of the facility to re-evaluate and increase
the response equipment necessary to adequately respond to a worst case discharge
from the facility.
Date of Last Update: ___
(if
different from Facility Address) Qualified Individual(s): (attach additional sheets if more than one)
Name: _____
Position: _____
Work Address: _____
Home Address: _____
Emergency Phone Number:
( )
_____ Date of Oil Storage Start-up: _____ Current Operations: _____ _____ _____
Date(s) and Type(s) of Substantial Expansion(s): _____ _____
(Attach additional sheets if necessary)
(A) The information provided in this section shall describe what will be
needed in an actual emergency involving the discharge of oil or a combination of
hazardous substances and oil discharge. The Emergency Response Information
section of the plan must include the following components:
(1) The information provided in the Emergency Notification Phone List in
section 1.3.1 identifies and prioritizes the names and phone numbers of the
organizations and personnel that need to be notified immediately in the event of
an emergency. This section shall include all the appropriate phone numbers for
the facility. These numbers must be verified each time the plan is updated. The
contact list must be accessible to all facility employees to ensure that, in
case of a discharge, any employee on site could immediately notify the
appropriate parties.
(2) The Spill Response Notification Form in section 1.3.1 creates a checklist
of information that shall be provided to the National Response Center (NRC) and
other response personnel. All information on this checklist must be known at the
time of notification, or be in the process of being collected. This notification
form is based on a similar form used by the NRC. Note: Do not delay spill
notification to collect the information on the list.
(3) Section 1.3.2 provides a description of the facility's list of emergency
response equipment and location of the response equipment. When appropriate, the
amount of oil that emergency response equipment can handle and any limitations
(e.g., launching sites) must be described.
(4) Section 1.3.3 provides information regarding response equipment tests and
deployment drills. Response equipment deployment exercises shall be conducted to
ensure that response equipment is operational and the personnel who would
operate the equipment in a spill response are capable of deploying and operating
it. Only a representative sample of each type of response equipment needs to be
deployed and operated, as long as the remainder is properly maintained. If
appropriate, testing of response equipment may be conducted while it is being
deployed. Facilities without facility-owned response equipment must ensure that
the oil spill removal organization that is identified in the response plan to
provide this response equipment certifies that the deployment exercises have
been met. Refer to the National Preparedness for Response Exercise Program
(PREP) Guidelines (see Appendix E to this part, section 13, for availability),
which satisfy Oil Pollution Act (OPA) response exercise requirements.
(5) Section 1.3.4 lists the facility response personnel, including those
employed by the facility and those under contract to the facility for response
activities, the amount of time needed for personnel to respond, their
responsibility in the case of an emergency, and their level of response
training. Three different forms are included in this section. The Emergency
Response Personnel List shall be composed of all personnel employed by the
facility whose duties involve responding to emergencies, including oil
discharges, even when they are not physically present at the site. An example of
this type of person would be the Building Engineer-in-Charge or Plant Fire
Chief. The second form is a list of the Emergency Response Contractors (both
primary and secondary) retained by the facility. Any changes in contractor
status must be reflected in updates to the response plan. Evidence of contracts
with response contractors shall be included in this section so that the
availability of resources can be verified. The last form is the Facility
Response Team List, which shall be composed of both emergency response personnel
(referenced by job title/position) and emergency response contractors, included
in one of the two lists described above, that will respond immediately upon
discovery of an oil discharge or other emergency (i.e., the first people to
respond). These are to be persons normally on the facility premises or primary
response contractors. Examples of these personnel would be the Facility
Hazardous Materials (HAZMAT) Spill Team 1, Facility Fire Engine Company 1,
Production Supervisor, or Transfer Supervisor. Company personnel must be able to
respond immediately and adequately if contractor support is not available.
(6) Section 1.3.5 lists factors that must, as appropriate, be considered when
preparing an evacuation plan.
(7) Section 1.3.6 references the responsibilities of the qualified individual
for the facility in the event of an emergency.
(B) The information provided in the emergency response section will aid in
the assessment of the facility's ability to respond to a worst case discharge
and will identify additional assistance that may be needed. In addition, the
facility owner or operator may want to produce a wallet-size card containing a
checklist of the immediate response and notification steps to be taken in the
event of an oil discharge.
Phone Numbers: Were Materials Discharged? ___ (Y/N) Confidential? ___ (Y/N)
Meeting Federal Obligations to Report? ___ (Y/N) Date Called: ___
Calling for Responsible Party? ___ (Y/N) Time Called: ___
Time of Incident: ___ AM/PM Nearest City:________ State: ___ County: ____ Zip: ____
Distance from City: ___ Units of Measure: ___ Direction from City: ___
Section: ____ Township: ____ Range: ____ Borough: ____
Container Type: ___ Tank Oil Storage Capacity: ____ Units of Measure: ___
Facility Oil Storage Capacity: ____ Units of Measure: ___
Facility Latitude: ___ Degrees ___ Minutes ___ Seconds
Facility Longitude: ___ Degrees ___ Minutes ___ Seconds
Actions Taken to Correct, Control or Mitigate Incident:
Number of Injuries: ___ Number of Deaths: ___
Were there Evacuations? ___ (Y/N) Number Evacuated: ___
Was there any Damage? ___ (Y/N) Damage in Dollars (approximate):_____
Any information about the incident not recorded elsewhere in the report:
EPA? ___ (Y/N) USCG? ___ (Y/N) State? ___ (Y/N)
Other? ___ (Y/N) Describe: ______
Date of Last Update:___
Type Model Year
Number: _____
Capacity: ____ gal./min.
Daily Effective Recovery Rate: _____
Storage Location(s): _____
Date Fuel Last Changed: _____ 2. Boom --
Operational Status: _____ Type, Model, and
Year:_____
Type Model Year
Number: _____
3. Chemicals Stored (Dispersants listed on EPA's NCP Product Schedule) Were appropriate procedures used to receive approval for use of dispersants
in accordance with the NCP (40 CFR 300.910) and the Area Contingency Plan (ACP),
where applicable?___ (Y/N).
Name and State of On-Scene Coordinator (OSC) authorizing use: ___ .
Date Authorized: ___ .
4. Dispersant Dispensing Equipment -- Operational Status: ___ . 7. Communication Equipment (include operating frequency and channel and/or
cellular phone numbers) -- Operational Status: ___ 8. Fire Fighting and Personnel Protective Equipment -- Operational Status:
___ 9. Other (e.g., Heavy Equipment, Boats and Motors) -- Operational Status: ___
Date of Last Update:____
Date of Last Update:____
1.3.5.1 Based on the analysis of the
facility, as discussed elsewhere in the plan, a facility-wide evacuation plan
shall be developed. In addition, plans to evacuate parts of the facility that
are at a high risk of exposure in the event of a discharge or other release must
be developed. Evacuation routes must be shown on a diagram of the facility (see
section 1.9 of this appendix). When developing evacuation plans, consideration
must be given to the following factors, as appropriate:
(1) Location of stored materials;
(2) Hazard imposed by discharged material;
(3) Discharge flow direction;
(4) Prevailing wind direction and speed;
(5) Water currents, tides, or wave conditions (if applicable);
(6) Arrival route of emergency response personnel and response equipment;
(7) Evacuation routes;
(8) Alternative routes of evacuation;
(9) Transportation of injured personnel to nearest emergency medical
facility;
(10) Location of alarm/notification systems;
(11) The need for a centralized check-in area for evacuation validation (roll
call);
(12) Selection of a mitigation command center; and
(13) Location of shelter at the facility as an alternative to evacuation.
1.3.5.2 One resource that may be helpful
to owners or operators in preparing this section of the response plan is The
Handbook of Chemical Hazard Analysis Procedures by the Federal Emergency
Management Agency (FEMA), Department of Transportation (DOT), and EPA. The
Handbook of Chemical Hazard Analysis Procedures is available from: FEMA ,
Publication Office, 500 C. Street, S.W., Washington, DC 20472, (202) 646-3484.
1.3.5.3 As specified in §112.20(h)(1)(vi),
the facility owner or operator must reference existing community evacuation
plans, as appropriate.
The duties of the designated qualified individual are specified in
§112.20(h)(3)(ix). The qualified individual's duties must be described and be
consistent with the minimum requirements in §112.20(h)(3)(ix). In addition, the
qualified individual must be identified with the Facility Information in section
1.2 of the response plan.
This section requires the facility owner or operator to examine the
facility's operations closely and to predict where discharges could occur.
Hazard evaluation is a widely used industry practice that allows facility owners
or operators to develop a complete understanding of potential hazards and the
response actions necessary to address these hazards. The Handbook of Chemical
Hazard Analysis Procedures, prepared by the EPA, DOT, and the FEMA and the
Hazardous Materials Emergency Planning Guide (NRT-1), prepared by the
National Response Team are good references for conducting a hazard analysis.
Hazard identification and evaluation will assist facility owners or operators in
planning for potential discharges, thereby reducing the severity of discharge
impacts that may occur in the future. The evaluation also may help the operator
identify and correct potential sources of discharges. In addition, special
hazards to workers and emergency response personnel's health and safety shall be
evaluated, as well as the facility's oil spill history.
The Tank and Surface Impoundment (SI) forms, or their equivalent, that are
part of this section must be completed according to the directions below.
("Surface Impoundment" means a facility or part of a facility which is a natural
topographic depression, man-made excavation, or diked area formed primarily of
earthen materials (although it may be lined with man-made materials), which is
designed to hold an accumulation of liquid wastes or wastes containing free
liquids, and which is not an injection well or a seepage facility.) Similar
worksheets, or their equivalent, must be developed for any other type of storage
containers.
(1) List each tank at the facility with a separate and distinct identifier.
Begin aboveground tank identifiers with an "A" and belowground tank identifiers
with a "B", or submit multiple sheets with the aboveground tanks and belowground
tanks on separate sheets.
(2) Use gallons for the maximum capacity of a tank; and use square feet for
the area.
(3) Using the appropriate identifiers and the following instructions, fill in
the appropriate forms:
(a) Tank or SI number -- Using the aforementioned identifiers (A or B) or
multiple reporting sheets, identify each tank or SI at the facility that stores
oil or hazardous materials.
(b) Substance Stored -- For each tank or SI identified, record the material
that is stored therein. If the tank or SI is used to store more than one
material, list all of the stored materials.
(c) Quantity Stored -- For each material stored in each tank or SI, report
the average volume of material stored on any given day.
(d) Tank Type or Surface Area/Year -- For each tank, report the type of tank
(e.g., floating top), and the year the tank was originally installed. If the
tank has been refabricated, the year that the latest refabrication was completed
must be recorded in parentheses next to the year installed. For each SI, record
the surface area of the impoundment and the year it went into service.
(e) Maximum Capacity -- Record the operational maximum capacity for each tank
and SI. If the maximum capacity varies with the season, record the upper and
lower limits.
(f) Failure/Cause -- Record the cause and date of any tank or SI failure
which has resulted in a loss of tank or SI contents.
(4) Using the numbers from the tank and SI forms, label a schematic drawing
of the facility. This drawing shall be identical to any schematic drawings
included in the SPCC Plan.
(5) Using knowledge of the facility and its operations, describe the
following in writing:
(a) The loading and unloading of transportation vehicles that risk the
discharge of oil or release of hazardous substances during transport processes.
These operations may include loading and unloading of trucks, railroad cars, or
vessels. Estimate the volume of material involved in transfer operations, if the
exact volume cannot be determined.
(b) Day-to-day operations that may present a risk of discharging oil or
releasing a hazardous substance. These activities include scheduled venting,
piping repair or replacement, valve maintenance, transfer of tank contents from
one tank to another, etc. (not including transportation-related activities).
Estimate the volume of material involved in these operations, if the exact
volume cannot be determined.
(c) The secondary containment volume associated with each tank and/or
transfer point at the facility. The numbering scheme developed on the tables, or
an equivalent system, must be used to identify each containment area. Capacities
must be listed for each individual unit (tanks, slumps, drainage traps, and
ponds), as well as the facility total.
(d) Normal daily throughput for the facility and any effect on potential
discharge volumes that a negative or positive change in that throughput may
cause.
The vulnerability analysis shall address the potential effects (i.e., to
human health, property, or the environment) of an oil discharge. Attachment
C-III to Appendix C to this part provides a method that owners or operators
shall use to determine appropriate distances from the facility to fish and
wildlife and sensitive environments. Owners or operators can use a comparable
formula that is considered acceptable by the RA. If a comparable formula is
used, documentation of the reliability and analytical soundness of the formula
must be attached to the response plan cover sheet. This analysis must be
prepared for each facility and, as appropriate, must discuss the vulnerability
of:
(1) Water intakes (drinking, cooling, or other);
(2) Schools;
(3) Medical facilities;
(4) Residential areas;
(5) Businesses;
(6) Wetlands or other sensitive environments; 2 2Refer to the DOC/NOAA "Guidance for Facility and Vessel Response
Plans: Fish and Wildlife and Sensitive Environments" (See appendix E to this
part, section 13, for availability). (7) Fish and wildlife;
(8) Lakes and streams;
(9) Endangered flora and fauna;
(10) Recreational areas;
(11) Transportation routes (air, land, and water);
(12) Utilities; and
(13) Other areas of economic importance (e.g., beaches, marinas) including
terrestrially sensitive environments, aquatic environments, and unique habitats.
Each owner or operator shall analyze the probability of a discharge occurring
at the facility. This analysis shall incorporate factors such as oil discharge
history, horizontal range of a potential discharge, and vulnerability to natural
disaster, and shall, as appropriate, incorporate other factors such as tank age.
This analysis will provide information for developing discharge scenarios for a
worst case discharge and small and medium discharges and aid in the development
of techniques to reduce the size and frequency of discharges. The owner or
operator may need to research the age of the tanks the oil discharge history at
the facility.
Briefly describe the facility's reportable oil spill 3
3As described in 40 CFR part 110, reportable oil spills are those
that: (a) violate applicable water quality standards, or (b) cause a film or
sheen upon or discoloration of the surface of the water or adjoining shorelines
or cause a sludge or emulsion to be deposited beneath the surface of the water
or upon adjoining shorelines. (1) Date of discharge(s);
(2) List of discharge causes;
(3) Material(s) discharged;
(4) Amount discharged in gallons;
(5) Amount of discharge that reached navigable waters, if applicable;
(6) Effectiveness and capacity of secondary containment;
(7) Clean-up actions taken;
(8) Steps taken to reduce possibility of recurrence;
(9) Total oil storage capacity of the tank(s) or impoundment(s) from which
the material discharged;
(10) Enforcement actions;
(11) Effectiveness of monitoring equipment; and
(12) Description(s) of how each oil discharge was detected. The information solicited in this section may be similar to requirements in
40 CFR 112.4(a). Any duplicate information required by §112.4(a) may be
photocopied and inserted.
In this section, the owner or operator is required to provide a description
of the facility's worst case discharge, as well as a small and medium discharge,
as appropriate. A multi-level planning approach has been chosen because the
response actions to a discharge (i.e., necessary response equipment,
products, and personnel) are dependent on the magnitude of the discharge.
Planning for lesser discharges is necessary because the nature of the response
may be qualitatively different depending on the quantity of the discharge. The
facility owner or operator shall discuss the potential direction of the
discharge pathway.
1.5.1.1 To address multi-level planning
requirements, the owner or operator must consider types of facility-specific
discharge scenarios that may contribute to a small or medium discharge. The
scenarios shall account for all the operations that take place at the facility,
including but not limited to:
(1) Loading and unloading of surface transportation;
(2) Facility maintenance;
(3) Facility piping;
(4) Pumping stations and sumps;
(5) Oil storage tanks;
(6) Vehicle refueling; and
(7) Age and condition of facility and components.
1.5.1.2 The scenarios shall also consider
factors that affect the response efforts required by the facility. These include
but are not limited to:
(1) Size of the discharge;
(2) Proximity to downgradient wells, waterways, and drinking water intakes;
(3) Proximity to fish and wildlife and sensitive environments;
(4) Likelihood that the discharge will travel offsite (i.e.,
topography, drainage);
(5) Location of the material discharged (i.e., on a concrete pad or
directly on the soil);
(6) Material discharged;
(7) Weather or aquatic conditions (i.e., river flow);
(8) Available remediation equipment;
(9) Probability of a chain reaction of failures; and
(10) Direction of discharge pathway.
1.5.2.1 In this section, the owner or
operator must identify the worst case discharge volume at the facility.
Worksheets for production and non-production facility owners or operators to use
when calculating worst case discharge are presented in Appendix D to this part.
When planning for the worst case discharge response, all of the aforementioned
factors listed in the small and medium discharge section of the response plan
shall be addressed.
1.5.2.2 For onshore storage facilities and
production facilities, permanently manifolded oil storage tanks are defined as
tanks that are designed, installed, and/or operated in such a manner that the
multiple tanks function as one storage unit (i.e., multiple tank volumes are
equalized). In this section of the response plan, owners or operators must
provide evidence that oil storage tanks with common piping or piping systems are
not operated as one unit. If such evidence is provided and is acceptable to the
RA, the worst case discharge volume shall be based on the combined oil storage
capacity of all manifold tanks or the oil storage capacity of the largest single
oil storage tank within the secondary containment area, whichever is greater.
For permanently manifolded oil storage tanks that function as one storage unit,
the worst case discharge shall be based on the combined oil storage capacity of
all manifolded tanks or the oil storage capacity of the largest single tank
within a secondary containment area, whichever is greater. For purposes of the
worst case discharge calculation, permanently manifolded oil storage tanks that
are separated by internal divisions for each tank are considered to be single
tanks and individual manifolded tank volumes are not combined.
In this section, the facility owner or operator shall provide a detailed
description of the procedures and equipment used to detect discharges. A section
on discharge detection by personnel and a discussion of automated discharge
detection, if applicable, shall be included for both regular operations and
after hours operations. In addition, the facility owner or operator shall
discuss how the reliability of any automated system will be checked and how
frequently the system will be inspected.
In this section, facility owners or operators shall describe the procedures
and personnel that will detect any discharge of oil or release of a hazardous
substance. A thorough discussion of facility inspections must be included. In
addition, a description of initial response actions shall be addressed. This
section shall reference section 1.3.1 of the response plan for emergency
response information.
In this section, facility owners or operators must describe any automated
discharge detection equipment that the facility has in place. This section shall
include a discussion of overfill alarms, secondary containment sensors, etc. A
discussion of the plans to verify an automated alarm and the actions to be taken
once verified must also be included.
In this section, facility owners or operators must explain in detail how to
implement the facility's emergency response plan by describing response actions
to be carried out under the plan to ensure the safety of the facility and to
mitigate or prevent discharges described in section 1.5 of the response plan.
This section shall include the identification of response resources for small,
medium, and worst case discharges; disposal plans; and containment and drainage
planning. A list of those personnel who would be involved in the cleanup shall
be identified. Procedures that the facility will use, where appropriate or
necessary, to update their plan after an oil discharge event and the time frame
to update the plan must be described.
1.7.1.1 Once the discharge scenarios have
been identified in section 1.5 of the response plan, the facility owner or
operator shall identify and describe implementation of the response actions. The
facility owner or operator shall demonstrate accessibility to the proper
response personnel and equipment to effectively respond to all of the identified
discharge scenarios. The determination and demonstration of adequate response
capability are presented in Appendix E to this part. In addition, steps to
expedite the cleanup of oil discharges must be discussed. At a minimum, the
following items must be addressed:
(1) Emergency plans for spill response;
(2) Additional response training;
(3) Additional contracted help;
(4) Access to additional response equipment/experts; and
(5) Ability to implement the plan including response training and practice
drills.
1.7.1.2A recommended form detailing immediate actions follows.
1.7.2.1 Facility owners or operators must
describe how and where the facility intends to recover, reuse, decontaminate, or
dispose of materials after a discharge has taken place. The appropriate permits
required to transport or dispose of recovered materials according to local,
State, and Federal requirements must be addressed. Materials that must be
accounted for in the disposal plan, as appropriate, include:
(1) Recovered product;
(2) Contaminated soil;
(3) Contaminated equipment and materials, including drums, tank parts,
valves, and shovels;
(4) Personnel protective equipment;
(5) Decontamination solutions;
(6) Adsorbents; and
(7) Spent chemicals.
1.7.2.2 These plans must be prepared in
accordance with Federal (e.g., the Resource Conservation and Recovery Act
[RCRA]), State, and local regulations, where applicable. A copy of the disposal
plans from the facility's SPCC Plan may be inserted with this section, including
any diagrams in those plans.
A proper plan to contain and control a discharge through drainage may limit
the threat of harm to human health and the environment. This section shall
describe how to contain and control a discharge through drainage, including:
(1) The available volume of containment (use the information presented in
section 1.4.1 of the response plan);
(2) The route of drainage from oil storage and transfer areas;
(3) The construction materials used in drainage troughs;
(4) The type and number of valves and separators used in the drainage system;
(5) Sump pump capacities;
(6) The containment capacity of weirs and booms that might be used and their
location (see section 1.3.2 of this appendix); and
(7) Other cleanup materials.
In addition, a facility owner or operator must meet the inspection and
monitoring requirements for drainage contained in 40 CFR part 112, subparts A
through C. A copy of the containment and drainage plans that are required in 40
CFR part 112, subparts A through C may be inserted in this section, including
any diagrams in those plans.
Note: The general permit for stormwater drainage may contain
additional requirements.
The owner or operator must develop programs for facility response training
and for drills/exercises according to the requirements of 40 CFR 112.21. Logs
must be kept for facility drills/exercises, personnel response training, and
spill prevention meetings. Much of the recordkeeping information required by
this section is also contained in the SPCC Plan required by 40 CFR 112.3. These
logs may be included in the facility response plan or kept as an annex to the
facility response plan.
Under 40 CFR 112.7(e), you must include the written procedures and records of
inspections for each facility in the SPCC Plan. You must include the inspection
records for each container, secondary containment, and item of response
equipment at the facility. You must cross-reference the records of inspections
of each container and secondary containment required by 40 CFR 112.7(e) in the
facility response plan. The inspection record of response equipment is a new
requirement in this plan. Facility self-inspection requires two-steps: (1) a
checklist of things to inspect; and (2) a method of recording the actual
inspection and its findings. You must note the date of each inspection. You must
keep facility response plan records for five years. You must keep SPCC records
for three years.
The tank inspection checklist presented below has been included as guidance
during inspections and monitoring. Similar requirements exist in 40 CFR part
112, subparts A through C. Duplicate information from the SPCC Plan may be
photocopied and inserted in this section. The inspection checklist consists of
the following items:
1. Check tanks for leaks, specifically looking for:
2. Check foundation for: 3. Check piping for:
Using the Emergency Response Equipment List provided in section 1.3.2 of the
response plan, describe each type of response equipment, checking for the
following: 1. Inventory (item and quantity);
2. Storage location;
3. Accessibility (time to access and respond);
4. Operational status/condition;
5. Actual use/testing (last test date and frequency of testing); and
6. Shelf life (present age, expected replacement date). Please note any discrepancies between this list and the available response
equipment.
Inspect the secondary containment (as described in sections 1.4.1 and 1.7.2
of the response plan), checking the following: 1. Dike or berm system. 2. Secondary containment 3. Retention and drainage ponds The tank inspection checklist presented below has been included as guidance
during inspections and monitoring. Similar requirements exist in 40 CFR part
112, subparts A through C. Similar requirements exist in 40 CFR 112.7(e).
Duplicate information from the SPCC Plan may be photocopied and inserted in this
section.
(A) CWA section 311(j)(5), as amended by OPA, requires the response plan to
contain a description of facility drills/exercises. According to 40 CFR
112.21(c), the facility owner or operator shall develop a program of facility
response drills/exercises, including evaluation procedures. Following the PREP
guidelines (see Appendix E to this part, section 13, for availability) would
satisfy a facility's requirements for drills/exercises under this part.
Alternately, under §112.21(c), a facility owner or operator may develop a
program that is not based on the PREP guidelines. Such a program is subject to
approval by the Regional Administrator based on the description of the program
provided in the response plan.
(B) The PREP Guidelines specify that the facility conduct internal and
external drills/exercises. The internal exercises include: qualified individual
notification drills, spill management team tabletop exercises, equipment
deployment exercises, and unannounced exercises. External exercises include Area
Exercises. Credit for an Area or Facility-specific Exercise will be given to the
facility for an actual response to a discharge in the area if the plan was
utilized for response to the discharge and the objectives of the Exercise were
met and were properly evaluated, documented, and self-certified.
(C) Section 112.20(h)(8)(ii) requires the facility owner or operator to
provide a description of the drill/exercise program to be carried out under the
response plan. Qualified Individual Notification Drill and Spill Management Team
Tabletop Drill logs shall be provided in sections 1.8.2.1 and 1.8.2.2,
respectively. These logs may be included in the facility response plan or kept
as an annex to the facility response plan. See section 1.3.3 of this appendix
for Equipment Deployment Drill Logs.
Section 112.21(a) requires facility owners or operators to develop programs
for facility response training. Facility owners or operators are required by
§112.20(h)(8)(iii) to provide a description of the response training program to
be carried out under the response plan. A facility's training program can be
based on the USCG's Training Elements for Oil Spill Response, to the extent
applicable to facility operations, or another response training program
acceptable to the RA. The training elements are available from the USCG Office
of Response (G-MOR) at (202) 267-0518 or fax (202) 267-4085. Personnel response
training logs and discharge prevention meeting logs shall be included in
sections 1.8.3.1 and 1.8.3.2 of the response plan respectively. These logs may
be included in the facility response plan or kept as an annex to the facility
response plan.
The facility-specific response plan shall include the following diagrams.
Additional diagrams that would aid in the development of response plan sections
may also be included. (1) The Site Plan Diagram shall, as appropriate, include and identify:
(2) The Site Drainage Plan Diagram shall, as appropriate, include:
(3) The Site Evacuation Plan Diagram shall, as appropriate, include:
According to 40 CFR 112.7(g) facilities are required to maintain a certain
level of security, as appropriate. In this section, a description of the
facility security shall be provided and include, as appropriate: (1) emergency cut-off locations (automatic or manual valves);
(2) enclosures (e.g., fencing, etc.);
(3) guards and their duties, day and night;
(4) lighting;
(5) valve and pump locks; and
(6) pipeline connection caps. The SPCC Plan contains similar information. Duplicate information may be
photocopied and inserted in this section.
A three-page form has been developed to be completed and submitted to the RA
by owners or operators who are required to prepare and submit a
facility-specific response plan. The cover sheet (Attachment F-1) must accompany
the response plan to provide the Agency with basic information concerning the
facility. This section will describe the Response Plan Cover Sheet and provide
instructions for its completion.
Owner/Operator of Facility: Enter the name of the owner of the
facility (if the owner is the operator). Enter the operator of the facility if
otherwise. If the owner/operator of the facility is a corporation, enter the
name of the facility's principal corporate executive. Enter as much of the name
as will fit in each section.
(1) Facility Name: Enter the proper name of the facility.
(2) Facility Address: Enter the street address, city, State, and zip
code.
(3) Facility Phone Number: Enter the phone number of the facility.
(4) Latitude and Longitude: Enter the facility latitude and longitude
in degrees, minutes, and seconds.
(5) Dun and Bradstreet Number: Enter the facility's Dun and Bradstreet
number if available (this information may be obtained from public library
resources).
(6) North American Industrial Classification System (NAICS) Code: Enter the
facility's NAICS code as determined by the Office of Management and Budget (this
information may be obtained from public library resources.)
(7) Largest Oil Storage Tank Capacity: Enter the capacity in GALLONS
of the largest aboveground oil storage tank at the facility.
(8) Maximum Oil Storage Capacity: Enter the total maximum capacity in
GALLONS of all aboveground oil storage tanks at the facility.
(9) Number of Oil Storage Tanks: Enter the number of all aboveground
oil storage tanks at the facility.
(10) Worst Case Discharge Amount: Using information from the
worksheets in Appendix D, enter the amount of the worst case discharge in
GALLONS.
(11) Facility Distance to Navigable Waters: Mark the appropriate line
for the nearest distance between an opportunity for discharge (i.e., oil storage
tank, piping, or flowline) and a navigable water.
Using the flowchart provided in Attachment C-I to Appendix C to this part,
mark the appropriate answer to each question. Explanations of referenced terms
can be found in Appendix C to this part. If a comparable formula to the ones
described in Attachment C-III to Appendix C to this part is used to calculate
the planning distance, documentation of the reliability and analytical soundness
of the formula must be attached to the response plan cover sheet.
Complete this block after all other questions have been answered.
ACP: Area Contingency Plan
ASTM: American Society of Testing Materials
bbls: Barrels
bpd: Barrels per Day
bph: Barrels per Hour
CHRIS: Chemical Hazards Response Information System
CWA: Clean Water Act
DOI: Department of Interior
DOC: Department of Commerce
DOT: Department of Transportation
EPA: Environmental Protection Agency
FEMA: Federal Emergency Management Agency
FR: Federal Register
gal: Gallons
gpm: Gallons per Minute
HAZMAT: Hazardous Materials
LEPC: Local Emergency Planning Committee
MMS: Minerals Management Service (part of DOI)
NAICS: North American Industrial Classification System
NCP: National Oil and Hazardous Substances Pollution Contingency Plan
NOAA: National Oceanic and Atmospheric Administration (part of DOC)
NRC: National Response Center
NRT: National Response Team
OPA: Oil Pollution Act of 1990
OSC: On-Scene Coordinator
PREP: National Preparedness for Response Exercise Program
RA: Regional Administrator
RCRA: Resource Conservation and Recovery Act
RRC: Regional Response Centers
RRT: Regional Response Team
RSPA: Research and Special Programs Administration
SARA: Superfund Amendments and Reauthorization Act
SERC: State Emergency Response Commission
SDWA: Safe Drinking Water Act of 1986
SI: Surface Impoundment
SPCC: Spill Prevention, Control, and Countermeasures
USCG: United States Coast Guard
CONCAWE. 1982. Methodologies for Hazard Analysis and Risk Assessment in the
Petroleum Refining and Storage Industry. Prepared by CONCAWE's Risk Assessment
Ad-hoc Group.
U.S. Department of Housing and Urban Development. 1987. Siting of
HUD-Assisted Projects Near Hazardous Facilities: Acceptable Separation Distances
from Explosive and Flammable Hazards. Prepared by the Office of Environment and
Energy, Environmental Planning Division, Department of Housing and Urban
Development. Washington, DC.
U.S. DOT, FEMA and U.S. EPA. Handbook of Chemical Hazard Analysis Procedures.
U.S. DOT, FEMA and U.S. EPA. Technical Guidance for Hazards Analysis:
Emergency Planning for Extremely Hazardous Substances.
The National Response Team. 1987. Hazardous Materials Emergency Planning
Guide. Washington, DC.
The National Response Team. 1990. Oil Spill Contingency Planning, National
Status: A Report to the President. Washington, DC. U.S. Government Printing
Office.
Offshore Inspection and Enforcement Division. 1988. Minerals Management
Service, Offshore Inspection Program: National Potential Incident of
Noncompliance (PINC) List. Reston, VA.
This cover sheet will provide EPA with basic information concerning the
facility. It must accompany a submitted facility response plan. Explanations and
detailed instructions can be found in Appendix F. Please type or write legibly
in blue or black ink. Public reporting burden for the collection of this
information is estimated to vary from 1 hour to 270 hours per response in the
first year, with an average of 5 hours per response. This estimate includes time
for reviewing instructions, searching existing data sources, gathering the data
needed, and completing and reviewing the collection of information. Send
comments regarding the burden estimate of this information, including
suggestions for reducing this burden to: Chief, Information Policy Branch, Mail
Code: PM-2822, U.S. Environmental Protection Agency, Ariel Rios Building, 1200
Pennsylvania Avenue, NW., Washington, DC 20460; and to the Office of Information
and Regulatory Affairs, Office of Management and Budget, Washington D.C. 20503.
Owner/Operator of Facility: Facility Address (street address or route): _____ City, State, and U.S. Zip Code: _____ Latitude (Degrees: North): degrees, minutes, seconds Dun & Bradstreet Number: 1 1These numbers may be obtained from public library
resources. Largest Aboveground Oil Storage Tank Capacity (Gallons): Number of Aboveground Oil Storage Tanks: Longitude (Degrees: West): 0- Does the facility transfer oil over-water 2 2Explanations of the above-referenced terms can be found in
Appendix C to this part. If a comparable formula to the ones contained in
Attachment C-III is used to establish the appropriate distance to fish and
wildlife and sensitive environments or public drinking water intakes,
documentation of the reliability and analytical soundness of the formula must be
attached to this form. Does the facility have a total oil storage capacity greater than or equal to
1 million gallons and, within any storage area, does the facility lack secondary
containment 2 that is sufficiently large to contain the capacity of
the largest aboveground oil storage tank plus sufficient freeboard to allow for
precipitation? Does the facility have a total oil storage capacity greater than or equal to
1 million gallons and is the facility located at a distance 2 (as
calculated using the appropriate formula in Appendix C or a comparable formula)
such that a discharge from the facility could cause injury to fish and wildlife
and sensitive environments? 3 3For further description of fish and wildlife and sensitive
environments, see Appendices I, II, and III to DOC/NOAA's "Guidance for Facility
and Vessel Response Plans: Fish and Wildlife and Sensitive Environments" (see
Appendix E to this part, section 13, for availability) and the applicable
ACP. Does the facility have a total oil storage capacity greater than or equal to
1 million gallons and has the facility experienced a reportable oil spill
2 in an amount greater than or equal to 10,000 gallons within the
last 5 years? I certify under penalty of law that I have personally examined and am
familiar with the information submitted in this document, and that based on my
inquiry of those individuals responsible for obtaining information, I believe
that the submitted information is true, accurate, and complete. [59 FR 34122, July 1, 1994; 59 FR 49006, Sept. 26, 1994, as amended at
65 FR 40816, June 30, 2000; 65 FR 43840, July 14, 2000; 66 FR 34561, June 29,
2001; 67 FR 47152, July 17, 2002]
FACILITY INFORMATION FORM
City: ___ State: ___ Zip:
___
County: ___ Phone Number:
( )
___
Latitude: ___ Degrees ___ Minutes ___ Seconds
Longitude: ___ Degrees ___ Minutes ___ Seconds
Wellhead Protection Area: _____ Owner: _____
Owner Location (Street Address):_____
City: ___ State:___
Zip: ___
County: ___ Phone Number:
( ) ___
Operator (if not Owner): _____
EMERGENCY NOTIFICATION PHONE LIST WHOM TO NOTIFY
------------------------------------------------------------------------
Organization Phone No.
------------------------------------------------------------------------
1. National Response Center (NRC): 1-800-424-8802
------------------
1 1 2. Qualified Individual: .................
------------------
Evening Phone: .................
------------------
3. Company Response Team: .................
------------------
Evening Phone: .................
------------------
4. Federal On-Scene Coordinator (OSC) and/or Regional .................
Response Center (RRC):
------------------
Evening Phone(s): .................
------------------
Pager Number(s): .................
------------------
5. Local Response Team (Fire Dept./Cooperatives): .................
------------------
6. Fire Marshall: .................
------------------
Evening Phone: .................
------------------
7. State Emergency Response Commission (SERC): .................
------------------
Evening Phone: .................
------------------
8. State Police: .................
------------------
9. Local Emergency Planning Committee (LEPC): .................
------------------
10. Local Water Supply System: .................
------------------
Evening Phone: .................
------------------
11. Weather Report: .................
------------------
12. Local Television/Radio Station for Evacuation .................
Notification:
------------------
13. Hospitals: .................
------------------
------------------------------------------------------------------------
SPILL RESPONSE NOTIFICATION FORM
Day
( ) -
Evening
( ) -Company:_____
Organization Type:_____
Address:_____
_____
City:_____
State:_____
Zip:_____
_____
_____
_____
_____
Date of Incident:_____
Incident Address/Location:_____
_____
--------------------------------------------------------------------------------------------------------------------------------------------------------
Material Discharged
CHRIS Code Discharged quantity Unit of measure in water Quantity Unit of measure
--------------------------------------------------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------------------------------------------------------------------------------------------------
_____
_____
_____
_____
Medium Affected:_____
Description:_____
More
Information about Medium:_____
_____
_____
_____
_____
_____
FACILITY RESPONSE EQUIPMENT LIST
Size (length): ____ ft.
Containment Area: ____ sq. ft.
Storage Location:_____
----------------------------------------------------------------------------------------------------------------
Date Treatment Storage
Type Amount purchased capacity location
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------
Response
Type and year Capacity Storage time
location (minutes)
------------------------------------------------------------------------
------------------------------------------------------------------------
------------------------------------------------------------------------
------------------------------------------------------------------------
------------------------------------------------------------------------
5. Sorbents -- Operational Status: _____
Type and Year Purchased: _____
Amount: _____
Absorption Capacity (gal.): _____
Storage Location(s): _____ 6. Hand Tools --
Operational Status: _____
------------------------------------------------------------------------
Type and year Quantity Storage location
------------------------------------------------------------------------
------------------------------------------------------------------------
------------------------------------------------------------------------
------------------------------------------------------------------------
------------------------------------------------------------------------
------------------------------------------------------------------------
Storage location/
Type and year Quantity number
------------------------------------------------------------------------
------------------------------------------------------------------------
------------------------------------------------------------------------
------------------------------------------------------------------------
Type and year Quantity Storage location
------------------------------------------------------------------------
------------------------------------------------------------------------
------------------------------------------------------------------------
------------------------------------------------------------------------
------------------------------------------------------------------------
------------------------------------------------------------------------
Type and year Quantity Storage location
------------------------------------------------------------------------
------------------------------------------------------------------------
------------------------------------------------------------------------
------------------------------------------------------------------------
------------------------------------------------------------------------
Last Inspection or Response Equipment Test Date: _____
Inspection Frequency: _____ Last Deployment Drill Date: _____ Deployment
Frequency: _____ Oil Spill Removal Organization Certification (if applicable):
_____
Emergency Response Personnel
Company Personnel
--------------------------------------------------------------------------------------------------------------------------------------------------------
Responsibility during response
Name Phone \1\ Response time action Response training type/date
--------------------------------------------------------------------------------------------------------------------------------------------------------
1.
--------------------------------------------------------------------------------------------------------------------------------------------------------
2.
--------------------------------------------------------------------------------------------------------------------------------------------------------
3.
--------------------------------------------------------------------------------------------------------------------------------------------------------
4.
--------------------------------------------------------------------------------------------------------------------------------------------------------
5.
--------------------------------------------------------------------------------------------------------------------------------------------------------
6.
--------------------------------------------------------------------------------------------------------------------------------------------------------
7.
--------------------------------------------------------------------------------------------------------------------------------------------------------
8.
--------------------------------------------------------------------------------------------------------------------------------------------------------
9.
--------------------------------------------------------------------------------------------------------------------------------------------------------
10.
--------------------------------------------------------------------------------------------------------------------------------------------------------
11.
--------------------------------------------------------------------------------------------------------------------------------------------------------
12.
--------------------------------------------------------------------------------------------------------------------------------------------------------
\1\ Phone number to be used when person is not on-site.
Emergency Response Contractors
Date of Last Update: ____
----------------------------------------------------------------------------------------------------------------
Contractor Phone Response time Contract responsibility \1\
----------------------------------------------------------------------------------------------------------------
1.
----------------------------------------------------------------------------------------------------------------
--------------------------------------------
--------------------------------------------
2.
----------------------------------------------------------------------------------------------------------------
--------------------------------------------
--------------------------------------------
3.
----------------------------------------------------------------------------------------------------------------
--------------------------------------------
--------------------------------------------
4.
----------------------------------------------------------------------------------------------------------------
--------------------------------------------
--------------------------------------------
----------------------------------------------------------------------------------------------------------------
\1\ Include evidence of contracts/agreements with response contractors to ensure the availability of personnel
and response equipment.
Facility Response Team
Date of Last Update:____
----------------------------------------------------------------------------------------------------------------
Phone or pager number (day/
Team member Response time (minutes) evening)
----------------------------------------------------------------------------------------------------------------
Qualified Individual:
................................... /
----------------------------------------------------------------------------------------------------------------
................................... /
----------------------------------------------------------------------------------------------------------------
................................... /
----------------------------------------------------------------------------------------------------------------
................................... /
----------------------------------------------------------------------------------------------------------------
................................... /
----------------------------------------------------------------------------------------------------------------
................................... /
----------------------------------------------------------------------------------------------------------------
................................... /
----------------------------------------------------------------------------------------------------------------
................................... /
----------------------------------------------------------------------------------------------------------------
................................... /
----------------------------------------------------------------------------------------------------------------
................................... /
----------------------------------------------------------------------------------------------------------------
................................... /
----------------------------------------------------------------------------------------------------------------
................................... /
----------------------------------------------------------------------------------------------------------------
................................... /
----------------------------------------------------------------------------------------------------------------
................................... /
----------------------------------------------------------------------------------------------------------------
................................... /
----------------------------------------------------------------------------------------------------------------
................................... /
----------------------------------------------------------------------------------------------------------------
................................... /
----------------------------------------------------------------------------------------------------------------
................................... /
----------------------------------------------------------------------------------------------------------------
Note: If the facility uses contracted help in an emergency response situation, the owner or operator must
provide the contractors' names and review the contractors' capacities to provide adequate personnel and
response equipment.
Hazard Identification Tanks \1\
Date of Last Update: ____
--------------------------------------------------------------------------------------------------------------------------------------------------------
Substance Stored (Oil
Tank No. and Hazardous Quantity Stored Tank Type/Year Maximum Capacity Failure/Cause
Substance) (gallons) (gallons)
--------------------------------------------------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------------------------------------------------------------------------------------------------
\1\ Tank = any container that stores oil.
Attach as many sheets as necessary.
Hazard Identification Surface Impoundments (SIs)
Date of Last Update: ____
--------------------------------------------------------------------------------------------------------------------------------------------------------
Quantity Stored Maximum Capacity
SI No. Substance Stored (gallons) Surface Area/Year (gallons) Failure/Cause
--------------------------------------------------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------------------------------------------------------------------------------------------------
Attach as many sheets as necessary.
Oil Spill Response_Immediate Actions
------------------------------------------------------------------------
1. Stop the product flow.................. Act quickly to secure pumps,
close valves, etc.
2. Warn personnel......................... Enforce safety and security
measures.
3. Shut off ignition sources.............. Motors, electrical circuits,
open flames, etc.
4. Initiate containment................... Around the tank and/or in
the water with oil boom.
5. Notify NRC............................. 1-800-424-8802
6. Notify OSC
7. Notify, as appropriate
------------------------------------------------------------------------
Source: FOSS, Oil Spill Response_Emergency Procedures, Revised December
3, 1992.
------------------------------------------------------------------------
Disposal RCRA permit/
Material facility Location manifest
------------------------------------------------------------------------
1.
------------------------------------------------------------------------
2.
------------------------------------------------------------------------
3.
------------------------------------------------------------------------
4.
------------------------------------------------------------------------
TANK INSPECTION CHECKLIST
A. drip marks;
B.
discoloration of tanks;
C. puddles containing
spilled or leaked material;
D. corrosion;
E. cracks; and
F. localized dead vegetation.
A. cracks;
B. discoloration;
C. puddles containing spilled or leaked
material;
D. settling;
E. gaps between tank and foundation; and
F. damage caused by vegetation roots.
A. droplets of stored
material;
B. discoloration;
C. corrosion;
D.
bowing of pipe between supports;
E. evidence of
stored material seepage from valves or seals; and
F. localized dead vegetation. Tank/Surface Impoundment Inspection Log
----------------------------------------------------------------------------------------------------------------
Inspector Tank or SI# Date Comments
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
Response Equipment Inspection Log
[Use section 1.3.2 of the response plan as a checklist]
----------------------------------------------------------------------------------------------------------------
Inspector Date Comments
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------
A. Level of precipitation
in dike/available capacity;
B. Operational
status of drainage valves;
C. Dike or berm
permeability;
D. Debris;
E. Erosion;
F.
Permeability of the earthen floor of diked area; and
G. Location/status of pipes, inlets, drainage
beneath tanks, etc.
A. Cracks;
B. Discoloration;
C. Presence of spilled or leaked material
(standing liquid);
D. Corrosion; and
E. Valve conditions.
A. Erosion;
B. Available capacity;
C. Presence of spilled or leaked material;
D. Debris; and
E. Stressed vegetation.
Date:_____ Company:_____ Qualified Individual(s):_____
Emergency Scenario:_____ _____ _____ Evaluation:_____ _____ _____ _____ Changes
to be Implemented:_____ _____ _____ Time Table for Implementation:_____ _____
Date:_____ Company:_____ Qualified Individual(s):_____
Emergency Scenario:_____ _____ _____ Evaluation:_____ _____ _____ _____ Changes
to be Implemented:_____ _____ _____ Time Table for Implementation:_____
Personnel Response Training Log
------------------------------------------------------------------------
Response training/ Prevention training/
Name date and number of date and number of
hours hours
------------------------------------------------------------------------
------------------------------------------------------------------------
------------------------------------------------------------------------
------------------------------------------------------------------------
------------------------------------------------------------------------
------------------------------------------------------------------------
------------------------------------------------------------------------
------------------------------------------------------------------------
------------------------------------------------------------------------
------------------------------------------------------------------------
------------------------------------------------------------------------
DISCHARGE PREVENTION MEETING LOG
Attendees:_____
_____
_____
_____
_____
_____
_____
_____
_____
------------------------------------------------------------------------
Subject/issue identified Required action Implementation date
------------------------------------------------------------------------
------------------------------------------------------------------------
------------------------------------------------------------------------
------------------------------------------------------------------------
------------------------------------------------------------------------
------------------------------------------------------------------------
------------------------------------------------------------------------
------------------------------------------------------------------------
(A) the entire facility to scale;
(B) above and below ground bulk oil storage
tanks;
(C) the contents and capacities of bulk
oil storage tanks;
(D) the contents and capacity
of drum oil storage areas;
(E) the contents and
capacities of surface impoundments;
(F) process
buildings;
(G) transfer areas;
(H) secondary containment systems (location and
capacity);
(I) structures where hazardous
materials are stored or handled, including materials stored and capacity of
storage;
(J) location of communication and
emergency response equipment;
(K) location of
electrical equipment which contains oil; and
(L)
for complexes only, the interface(s) (i.e., valve or component) between the
portion of the facility regulated by EPA and the portion(s) regulated by other
Agencies. In most cases, this interface is defined as the last valve inside
secondary containment before piping leaves the secondary containment area to
connect to the transportation-related portion of the facility (i.e., the
structure used or intended to be used to transfer oil to or from a vessel or
pipeline). In the absence of secondary containment, this interface is the valve
manifold adjacent to the tank nearest the transfer structure as described above.
The interface may be defined differently at a specific facility if agreed to by
the RA and the appropriate Federal official.
(A) major sanitary and storm sewers, manholes, and
drains;
(B) weirs and shut-off valves;
(C) surface water receiving streams;
(D) fire fighting water sources;
(E) other utilities;
(F) response personnel ingress and egress;
(G) response equipment transportation routes;
and
(H) direction of discharge flow from
discharge points.
(A) site plan diagram with evacuation route(s); and
(B) location of evacuation regrouping areas.
ATTACHMENTS TO APPENDIX F
GENERAL INFORMATION
_____
Facility Name: _____
_____
Facility Phone No.: _____
_____
_____
_____
_____
_____ degrees, minutes, seconds _____
North American Industrial Classification System (NAICS) Code:
1 _____
_____
Maximum Oil Storage Capacity
(Gallons): _____
Worst Case Oil Discharge Amount (Gallons): _____
Facility Distance to Navigable Water. Mark the appropriate line. _____
APPLICABILITY OF SUBSTANTIAL HARM CRITERIA
Yes _____ No _____
Yes _____
No_____
Yes _____
No_____
Does the
facility have a total oil storage capacity greater than or equal to 1 million
gallons and is the facility located at a distance 2 (as calculated
using the appropriate formula in Appendix C or a comparable formula) such that a
discharge from the facility would shut down a public drinking water intake?
2 _____
Yes _____
No _____
Yes _____
No _____
CERTIFICATION
Signature: _____
Name (Please type or print): _____
_____
Title: _____
Date: _____