by Thomas and Michael Kovacic
Electrical safety on construction sites continues to be a major
issue. While progress has been made over the years, electrical
accidents continue to rank high on the list of construction
accidents. In some areas of the country, they are the second leading
cause of death or serious injury.
One reason that electrical accidents occur is because of
confusion between National Fire Protection Association (NFPA) and
OSHA requirements. Four areas in particular continue to spark
controversy or are approached differently by different regulatory
standards. There are ways to bring harmony to these four issues by
providing recommendations to deal with the differences.
GFCIs and Portable Generators
Ground-fault circuit-interrupters (GFCIs) continue to be a very
cost-effective form of protection for cord- and plug-connected
equipment on construction sites. With the introduction of the 2002
edition of NFPA's National Electrical Code (NEC), however,
differences have appeared between NEC and OSHA.
Since 1971, there has been an exception to the GFCI requirement
by NEC for outlets on portable generators. In the 1999 NEC, it was
Exception No. 1 to 305-6(a). In the OSHA regulation, it is found in
1926.404(b)(1)(ii). It reads:
"Receptacles on a two-wire, single-phase portable or
vehicle-mounted generator rated not more than 5 kW, where the
circuit conductors of the generator are insulated from the generator
frame and all other grounded surfaces, need not be protected with
ground-fault circuit interrupters."
This exception has been removed from the 2002 edition of the NEC.
The reasoning is that Article 250 requires that 120-volt generators
have one wire of the generator winding connected to the generator
frame (grounded). The generator described in 1926.404(b)(1)(ii) is
commonly referred to as an "isolated winding" generator. The NEC,
and specifically Article 250, does not permit such a generator.
What does this mean for you? OSHA will continue to allow the use
of an "isolated winding" generator without the use of a GFCI, as
long as the generator meets all of the stated requirements. Some
states with a state OSHA plan may not, and there are reports that
many local authorities are enforcing the 2002 NEC requirements.
What should you do? The main concern should be the safety of all
employees. GFCIs are inexpensive and provide a higher level of
protection than an "isolated winding" generator. Do not get involved
in these enforcement issues; simply follow NEC requirements.
Additionally, many new generators have a GFCI receptacle
installed by the manufacturer. These generators and the GFCI outlets
are not suitable for use in wet locations. Thus, they require
additional protection when used outdoors.
Personnel are required to use a GFCI whenever cord- and
plug-connected tools are used for construction or maintenance
purposes. The GFCI must be installed as close to the source of power
as is practical. When using portable-type GFCIs, do not use
extension cord sets between the GFCI and the source of power.
Open Wiring on Insulators
Open wiring on insulators for temporary lighting and, in some
cases, receptacle outlets, has been a common wiring method used on
construction sites. Prior to the 1996 NEC, Section 305-4(b) and (c)
allowed such wiring for feeders and/or branch circuits not exceeding
150 volts to ground. Beginning with the 1996 NEC, this wiring method
is prohibited. It is only permitted for emergencies and tests. In
the 2002 NEC edition, this section has been relocated to Section
527.4(B) and (C).
What does this mean for you? As with GFCIs, OSHA will continue to
enforce its regulations. 1910.305(a)(2)(iii)(A) & (B) and
1926.405(a)(2)(ii)(A) & (B) permit open wiring on insulators
provided the installation meets all of the requirements. Many
inspection authorities were never comfortable with open wiring on
insulators because of the possible exposure to physical damage.
Thus, many will enforce NEC requirements regardless of what OSHA
will accept.
What should you do? After years of electrical safety inspections,
we tend to agree with those who do not like this method of temporary
wiring. In the early days, there were limited cord assemblies
available, and the quality was poor. Today, numerous manufacturers
have cord assemblies with molded-on lamp holders with proper lamp
guards at a reasonable cost. They are easy and time-efficient to
install and can be reused job after job. Avoid the unnecessary
hassle of enforcement differences between local and federal
authorities.
Under some circumstances, cable assemblies such as
nonmetallic-sheath cable may be used. Such cable assemblies must be
suitable for the environment. For example, nonmetallic-sheath cable
cannot be used in wet locations. Some cable assemblies may not be
listed for exposure to sunlight.
Relocatable Power Taps
Relocatable power taps (RPTs), previously called temporary power
taps, continue to be found on construction sites. Although
convenient and inexpensive, they are not intended for use at
construction sites and similar locations, nor can they be used
outdoors. These limitations can be found in the UL Directory titled
General Information for Electrical Equipment - 2002 edition
(frequently referred to as the UL White Book).
Although these devices appear to be adequate, when UL or any
other nationally recognized testing laboratory (NRTL) evaluates a
product, the application conditions described in the product
standard will establish the criteria for the evaluation process. If
a product is not intended for certain uses, the standard will not
include criteria that may be important for safe use in that
application.
There is also confusion in the marketing of these devices. Many
otherwise quality products have been found in the marketplace with
packaging that indicates they are suitable for use at construction
sites, outdoor locations or for use with heavy construction-type
equipment. All this is in conflict with the UL White Book
information. Under Section 110.3(b) and OSHA's 1926.403(b)(2), the
product must be used in accordance with its intended use as
described by an NRTL.
What does this mean for you? There is mixed input from the field
on the consistency of enforcement regarding this issue. The OSHA
compliance officer must take into account numerous factors that will
have a bearing on whether a citation is issued. Many local
authorities are not even going into these areas simply because of
the time limitation on them to get their inspection completed.
What should you do? Many times RPTs are used because they are
convenient and inexpensive. Don't adopt this attitude. Use the
correct product for the job. In most instances, use an extension
cord set with multiple outlets. Such extension cord sets are
available and listed for the application. In some cases, they can be
field-fabricated using all listed components applied correctly.
RPTs can be used in construction trailers and similar office-type
structures. The best rule to keep in mind when applying an RPT is
that they are intended for use where there is a high concentration
of low-powered loads. If this simple rule is followed, an unsafe
application will be avoided.
Arc-Blast and Arc-Flash Hazards
One of the most important issues discussed is the application of
NFPA 70E to construction site activity and, particularly, the flash
hazard issue. This issue has not been well-addressed in the
construction industry even though there is a significant risk.
Electrical accident fatality data indicates that a high number of
fatalities occur each year among electricians due to an arc blast or
arc flash. The data indicates that 80 percent of the fatalities
among qualified persons is due to a burn-related incident.
The possibility of an arc flash and the extreme amount of heat
that it produces is not new information. In 1990, OSHA promulgated
its electrical safety-related work practices regulations. OSHA did
not specifically mention arc-flash hazard. Its approach was to be
somewhat performance-oriented and let the employer assume the
responsibility of determining what hazards were present and how they
would be addressed.
This approach did not work as well as some may have anticipated,
and another important document had to assume the responsibility of
being more specific. This document is NFPA 70E - Standard for
Electrical Safety for Employee Workplaces, 2000 Edition. Section
2-1.3.3 in Part II states that a flash hazard analysis must be
performed before an employee can approach any exposed electrical
conductor or circuit part that has not been placed in an
electrically safe work condition.
In the last few years, considerable progress has been made in
industrial facilities after the owners take occupancy. It is during
the construction phase that there is little or no attention to this
hazard. In many of our code classes for construction electricians,
the majority states that this is the first time they have heard
about this issue.
What does this mean for you? It is not unusual during
construction to be working on electrical equipment that is energized
and has the cover and enclosure doors open. As the need for power
increases and more system stability is demanded, the impedance of
transformers is becoming quite low. It also is not unusual to find
services for commercial and industrial buildings with the available
fault current as high as 65,000 amperes. Even some residential
services can be a problem.
If an accident should occur and an arc is initiated in such a
system, the heat from the arc could be as high as 40 calories per
cm2. This is more than three times the heat needed to ignite typical
work clothing an electrician may wear. The catastrophic forces
associated with arc blast/arc flash can destroy the electrical
equipment and fatally burn anyone within an 8-foot radius.
What should you do? If you have not done it already, acquire a
copy of the 2002 edition of NFPA 70E. Become familiar with how a
fault current study is done and how to perform a flash hazard
analysis. This will add cost to the job, but it will be far less
expensive than having an unexpected fatality.
Everyone on the construction site could be exposed to such
hazards. Once the flash hazard analysis is completed, proper
clothing will be required for construction electricians when working
on energized equipment while enclosure covers have been opened or
removed. When such work is being performed, a flash protection
boundary must be established, and all unqualified and unprotected
workers will have to remain outside said boundary.
Construction site safety managers should become familiar with
these requirements and verify that all trades are properly trained
to avoid a flash hazard.
It is interesting that the 2002 NEC also is beginning to address
the importance of a flash hazard. Section 110.116 requires that
electrical equipment be field-marked to warn qualified persons of
potential electric arc-flash hazards. A generic sign that meets the
NEC and local AHJ requirements normally will be adequate initially.
It is recommended, however, that a more complete marking be provided
after occupancy.
Conclusion
Although there are additional electrical safety issues associated
with construction work, these four need to attract the most
attention. The first three are reasonably easy to address and have
been discussed for years. Flash hazard, however, is a newer issue in
the construction industry. It is a major issue that has not been
well-addressed and needs to be given serious consideration.
Thomas Kovacic is president of TMK and Associates Inc., a
Cleveland company that provides electrical safety consultation
worldwide. Michael Kovacic is vice president of operations for TMK.
TMK and Associates Inc. provides services such as training and
education, fault current studies and flash hazard analysis, safety
assessments, policy creation and revision, grounding and power
quality studies, accident investigation and expert witness
testimony. Visit its Web site at
www.oshazone.com.
by Thomas and Michael Kovac ()
Copyright ©
2002 Penton Media, Inc.
Copyright Notice |
Privacy Policy